Opportunity summary
The project is early enough to monitor before main construction procurement.
- Stage
- Approved; demolition due late 2026; construction due mid-2027 · Early project signal
- Cabinetry scope
- Apartment kitchens, vanities, wardrobes, laundries and communal-room joinery.
- The project will deliver 114 social homes.
- It comprises two eight-storey residential buildings.
- Approval was granted on 22 June 2026.
- Demolition is scheduled for late 2026.
- Construction is due to commence by mid-2027.
- Link Wentworth will manage construction and later tenancy services.
- A head-builder or trade procurement phase may occur before mid-2027.
- The cabinetry package is likely to require commercial-scale capacity.
These are reasoned inferences, not statements from the issuing organisation.
- Has a head contractor been selected?
- Will Link Wentworth tender trade packages directly?
- When will supplier engagement begin?
Evidence
ScaleHomes NSW confirms 114 homes across two eight-storey buildings.
NSW Government · checked 8 Nov 2026
ApprovalThe project was approved on 22 June 2026.
NSW Government · checked 8 Nov 2026
ProgrammeDemolition is planned for late 2026 and construction by mid-2027.
NSW Government · checked 8 Nov 2026
Delivery roleLink Wentworth will manage construction and ongoing housing services.
NSW Government · checked 8 Nov 2026
DocumentsThe official page provides demolition plans and community notifications.
NSW Government · checked 8 Nov 2026